Our Implementation Plan begins with a one-week Project Kickoff, followed by two weeks of Stakeholder Meetings. A three-week Needs Assessment phase precedes a four-week Solution Design stage. Resource Allocation and Training Sessions span two and three weeks, respectively, leading to a two-week Pilot Implementation. The critical Full Implementation phase lasts four weeks, ensuring a comprehensive rollout. User Feedback and Iteration take three weeks, followed by two weeks for Finalization and Documentation. Finally, on February 15, 2024, we mark the Project Review and Closure milestone, wrapping up our implementation journey.
Edit this diagram in Gleek
Implementation plan diagram code in Gleek
/g Implementation Plan
Project Kickoff
Done
2023-08-01
1w
Stakeholder Meetings
Done
=> Project Kickoff
2w
Needs Assessment
Done
=> Stakeholder Meetings
3w
Solution Design
Active
=> Needs Assessment
4w
Resource Allocation
Active
=> Solution Design
2w
Training Sessions
Active
=> Resource Allocation
3w
Pilot Implementation
Active
=> Training Sessions
2w
Full Implementation
Critical
=> Pilot Implementation
4w
User Feedback and Iteration
Active
=> Full Implementation
3w
Finalization and Documentation
Active
=> User Feedback and Iteration
2w
Project Review and Closure
Milestone
=> Finalization and Documentation
2024-02-15
About Gantt charts
Gantt charts, named after Henry Gantt, aid in project organization and monitoring, showcasing task timelines, durations, and overlaps. They're versatile tools used across industries, offering an overview of project lifecycles, beneficial for planning, resource allocation, and stakeholder communication. These charts assist in scheduling, dependency identification, and progress visualization, enhancing task management and resource allocation for effective project execution.