Our Supply Chain Management journey begins with a two-week Market Analysis, followed by a critical three-week Supplier Identification phase. Over the next four to five weeks, we negotiate contracts and set up inventory and warehouse systems. As our infrastructure takes shape, we focus on transportation, quality control, packaging, and distribution network development, each lasting three to four weeks. Product delivery coordination follows, spanning three weeks, closely tied to our distribution network. We then enter cycles of three-week optimization, performance monitoring, supplier evaluation, audits, and enhancements, aiming for continuous improvement. Finally, on 2024-01-29, we mark a milestone with the Supply Chain Management Review, reflecting on our journey and setting the stage for further growth.
Edit this diagram in Gleek
Supply chain management diagram code in Gleek
/g Supply Chain Management
Market Analysis
Done
2023-07-01
2w
Supplier Identification
Critical
=> Market Analysis
3w
Contract Negotiation
Active
=> Supplier Identification
4w
Inventory Management System Setup
Active
=> Supplier Identification
4w
Warehouse Setup
Critical
=> Supplier Identification
5w
Transportation Logistics Planning
Active
=> Warehouse Setup
4w
Quality Control Proced. Implement.
Active
=> Warehouse Setup
3w
Packaging Design and Production
Active
=> Warehouse Setup
3w
Distribution Network Development
Active
=> Warehouse Setup
4w
Product Delivery Coordination
Active
=> Distribution Network Development
3w
Supply Chain Optimization
Active
=> Product Delivery Coordination
3w
Performance Monitor&Improve
Active
=> Supply Chain Optimization
3w
Continuous Supplier Evaluation
Active
=> Performance Monitor&Improve
3w
Supply Chain Audit
Active
=> Continuous Supplier Evaluation
2w
Supply Chain Enhance.
Active
=> Supply Chain Audit
2w
Supply Chain Management Review
Milestone
=> Supply Chain Enhance.
2024-01-29
About Gantt charts
Gantt charts, named after Henry Gantt, aid in project organization and monitoring, showcasing task timelines, durations, and overlaps. They're versatile tools used across industries, offering an overview of project lifecycles, beneficial for planning, resource allocation, and stakeholder communication. These charts assist in scheduling, dependency identification, and progress visualization, enhancing task management and resource allocation for effective project execution.
Similar gantt chart examples
Construction Project Management gantt chart
School management system project gantt chart
Implementation plan gantt chart
Website development gantt chart
App development project gantt chart
Research project proposal gantt chart